HIGHWAY 67/167 LANE CLOSURES AND TRAFFIC SHIFT TO OCCUR IN NORTH LITTLE ROCK LITTLE ROCK (11-12) Arkansas State Highway and Transportation Department
(AHTD) officials announce that SOUTHBOUND Highway 67/167 will be temporarily reduced to one
lane of travel on Monday November 15th between mile markers 1 and 3
beginning at 6 p.m. Lane closures
will begin after the afternoon rush hour with two lanes expected to be restored
prior to the next morning’s peak travel time at 6 a.m.
The closures are needed in order for construction crews to begin shifting
Highway 67/167 SOUTHBOUND traffic on to new concrete lanes between Wildwood
Avenue and McCain Boulevard, including the new bridge structure over Five Mile
Creek. Approximately one week after the southbound traffic
shift, the contractor will repeat the lane closure and traffic shift process for
the northbound lanes. Once this
transition is complete, two lanes in each direction will be traveling on the new
pavement and bridge structure while construction crews remove and replace the
original northbound side of the highway and build the other half of the Five
Mile Creek bridge. In addition to the traffic switch, a new southbound
entrance ramp at the Wildwood interchange from Warden Road to Hwy 67/167 will be
in place. This ramp is located
approximately 1,500 feet south of the original ramp location and is between the
Midas Muffler Shop and Tractor Supply Company on Warden Road.
Northbound traffic on Warden Road will continue to yield to traffic on
this ramp and several new yield signs have been installed to forewarn motorists
of the new ramp location. The closures and traffic shift are necessary in order
to progress to the next phase of construction as part of the $22.5 million
widening of Hwy. 67/167 in this area. The
contractor, Muskogee Bridge Company of Muskogee, OK, has been building the
southbound side of the Five Mile Creek underpass and new turnaround lanes at
McCain and Wildwood in addition to removing and replacing the southbound travel
lanes. During this time, southbound
motorists between Wildwood and McCain have been traveling on temporary lanes to
the eastern side of the roadway. All work will be done as weather permits with
possible rainfall forcing the transition schedule to begin at a later date.
Motorists are reminded to stay alert, avoid distractions and follow all
signs and speed limits in the work zone with doubled fines occurring for all
moving violations. Additional
details of this and other lane closures may be found by clicking on the ROADS
button at www.ArkansasHighways.com
for continuous updates to current and upcoming lane closure locations and time
frames. The AHTD Public Affairs
Office is available via phone at 501-569-2227 on Monday through Friday, 8:00
a.m. to 4:30 p.m., to assist motorists with construction information.