Arkansas Highway and Transportation Department - Lane Closures

Neither the map nor the text report show short-term lane closures (those where the lane is closed for less than 4 hours) or moving lane closures necessary for some maintenance or construction activities. For information on short-term closures or moving lane closures, please contact the District Engineer for the District or county in question. An underlined "Begin Date" represents planned closures.

Dist.CountyRouteSectionBegin Mile MarkerEnd Mile MarkerLane(s) ClosedBegin DateApprox. DaysTimeHor. Clr.UnitVert. Clr.Max. Width LoadComments................
5Stone51607.9112.14North & South Bound09/18/2013Ongoing24 Hours10.00FT13.509.50Job R50116. Moving lane closure in Alternating lanes.
6Garland709010.8011.50South Bound Outside10/08/2014409 A.M. - 3 P.M.12.00FT 9.00Water Utility Work - Central Avenue
8Pope71608.309.56Alternating North & South Bound09/15/2014Ongoing24 Hours13.00FT 10.00Shoulder work.
6Pulaski1008015.6515.77East Bound Outside11/14/2014609:AM-3:30 PM12.00FT 9.00Robinson Center Rehab project.
5Jackson1412011.4013.30East Bound11/14/201458:30am - 2:30 pm12.00FT 11.00Soil Investigation through bridge deck. Monday thru Thursday, Nov. 20th.
5Jackson1412011.4013.30Alternating East & West Bound11/24/2014Three (3)9:30 am - 2:30 pm12.00FT 11.00Soil Investigation, using deck as the platform.
4Washington160302.923.85East Bound09/05/2014Ongoing9:00 a.m.-5;00 p.m.11.00FT 9.00Width Restriction - All Lanes. Notch and Widening on South Side of the Road.
5Cleburne250306.406.50South Bound12/01/20141224 hours10.00FT 10.00Corps of Engineers working on dam at Heber Springs.
5Cleburne250306.406.50South Bound10/20/20143724 hours10.00FT 10.00Corps of Engineers working on dam.
8Yell271007.009.00North Bound10/27/2014ongoing24 hours10.00FT 10.00setting temporary precast concrete barrier wall as part of 080428
Dist.CountyRouteSectionBegin Mile MarkerEnd Mile MarkerLane(s) ClosedBegin DateApprox. DaysTimeHor. Clr.UnitVert. Clr.Max. Width LoadComments................
8Yell2710010.5012.20South Bound10/23/2014ongoing7 a.m. - 7 p.m.10.00FT 10.00Drainage System Installation.
8Yell2710010.5012.20Width Restriction Only07/30/2014ongoing24 Hours10.00FT 10.00Width Restriction - All Lanes.
3Hempstead3012022.3729.49East & West Bound11/14/2014156:00 a,m. - 7:00 p.m. FT 13.00Job BB0306. Width Restriction NO WIDE LOADS
6Pulaski30230129.72130.02Right Shoulder08/26/2014Ongoing24 Hours FT 18.00Job 061332 Precast Concrete Barrier Wall Installed on Outside Shoulder.
3Nevada320802.953.35All08/14/2012ONGOING24 HRS FT 10.00JOB 030386. DETOUR. WIDTH RESTRICTION. *NO WIDE LOADS*
8Johnson4021045.5047.00West Bound11/19/201426:30 a.m. - 6:30 p.m. FT  Misc work as per BB1103
8Johnson4021057.0061.00East Bound Outside12/08/201426:30 a.m. - 3:00 p.m.12.00FT 12.00Bridge construction as per job BB0803
8Johnson4021057.0061.00East Bound Inside12/04/201426:30 a.m. - 3:00 p.m.12.00FT 12.00Bridge construction as per BB0803
8Johnson4021057.0061.00West Bound Outside11/24/201426:30 a.m. - 3:00 p.m.12.00FT 12.00Bridge construction per job BB0803
8Johnson4021057.0061.00West Bound Inside12/02/201426:30 a.m. - 3:00 p.m.12.00FT 12.00Bridge construction as per BB0803
Dist.CountyRouteSectionBegin Mile MarkerEnd Mile MarkerLane(s) ClosedBegin DateApprox. DaysTimeHor. Clr.UnitVert. Clr.Max. Width LoadComments................
8Johnson4021063.5066.50East Bound Inside09/29/2014ongoing24 Hours12.00FT 12.00WRSF work as part of BB0803.
8Johnson4021063.5071.51East Bound Outside11/25/201427 a.m. - 7 p.m.12.00FT 12.00Asphalt Paving Operation as per BB0803.
8Johnson4021064.0071.51West Bound Inside11/19/201477 a.m. - 7 p.m.12.00FT 12.00Asphalt Paving Operation as per BB0803.
8Johnson4021064.0067.00West Bound Outside10/13/2014ongoing7 a.m. - 7 p.m.12.00FT 12.00Asphalt Paving Operation.
8Pope4022071.5173.00West Bound Inside11/19/201457:00 a.m. - 7:00 p.m.12.00FT 12.00Asphalt Paving Operation as per BB0803.
8Pope4022073.0081.00West Bound Outside01/14/2013Ongoing24 Hours17.00FT 14.00Crossover-both directions on Westbound side.
8Pope4022073.0081.00East Bound Outside01/14/2013Ongoing24 Hours16.00FT 13.00Crossover-both directions on Westbound side.
8Pope4022084.0094.50East Bound11/24/2014224 Hours16.00FT 13.00Moving lane closure in Alternating lanes.
8Pope4022084.0094.50West Bound11/24/2014224 Hours16.00FT 13.00Moving lane closure in Alternating lanes.
6Pulaski40330138.36142.50East Bound Outside11/17/2014Ongoing7:00 PM to 5:00am FT 12.00Job 012145 Rumble strips and final stripping
Dist.CountyRouteSectionBegin Mile MarkerEnd Mile MarkerLane(s) ClosedBegin DateApprox. DaysTimeHor. Clr.UnitVert. Clr.Max. Width LoadComments................
6Pulaski40330138.36143.00West Bound Outside11/17/2014Ongoing8:00 pm to 6:00 am FT 12.00Job 012145 Rumble strips and final stripping
6Pulaski40330142.00148.00East Bound Inside11/24/201428:00 pm to 6:00 am FT 12.00Job CA0609 Precast Barrier Wall installation
6Pulaski40330142.00149.00West Bound Inside11/24/201429:00 pm to 7:00 am FT 12.00Job CA0609 Precast Barrier Wall Installation
6Pulaski40330142.35147.46East Bound Inside12/02/201458 PM - 6 AM12.00FT 10.00Job CA0609 precast barrier wall installation
6Pulaski40330142.35147.46West Bound Inside12/02/201459 PM - 7 AM12.00FT 10.00Job CA0609 precast barrier wall installation
6Lonoke40410172.50174.00East Bound Inside10/13/2014Ongoing24 Hours FT 12.00Job 060897 Guardrail construction on inside shoulder
6Lonoke40410173.00175.00West Bound Inside10/13/2014Ongoing24 Hours FT 12.00Job 060897 Guardrail construction on inside shoulder
6Prairie40420198.00202.00West Bound Inside11/20/201418 a.m. - 3 p.m. FT 9.00Vacuum sweeping next to median barrier wall
6Prairie40420198.00202.00East Bound Inside11/19/201418 a.m. - 3 p.m. FT 9.00Vacuum sweeping next to median barrier wall
1Monroe40430205.41210.00West Bound06/24/2014Ongoing24 Hours11.00FT 8.50Job BB0101 - One lane, head to head on EB side
Dist.CountyRouteSectionBegin Mile MarkerEnd Mile MarkerLane(s) ClosedBegin DateApprox. DaysTimeHor. Clr.UnitVert. Clr.Max. Width LoadComments................
1Monroe40430205.42210.00East Bound07/01/2014Ongoing24 Hours11.00FT 8.50Job BB0101 Rumble strip removal, shoulder reconstruct, barrier wall
1St.-Francis40510228.23239.82Alternating East & West Bound08/04/2014Ongoing7:00 pm to 9:00 am12.00FT 9.00BB0104 - Alternating lane closures for punch list work.
1St.-Francis40510238.80249.12Alternating East & West Bound08/21/2014ongoing8:00 pm to 9:00 am12.00FT 9.00Job BB0105 - Night time lane closures Alternating for Stage 5C Construction.
1Crittenden40520277.07281.12East Bound Inside01/27/2014Ongoing24 Hours11.00FT 8.50Lane Closed for Bridge and Roadway work associated with BB0108.
1Crittenden40520277.57281.38West Bound Outside03/06/2014Ongoing24 Hours11.00FT 8.50For work associated with project BB0108.
4Washington4928063.7465.03North Bound09/23/2013Ongoing24 Hours22.00FT 18.00Width Restriction - Northbound Lanes Only. Both Shoulders Closed
4Washington4928063.7465.03South Bound09/23/2013Ongoing24 Hours22.00FT 18.00Width Restriction - Southbound Lanes Only. Both Shoulders Closed.
4Washington4928063.7465.03South Bound Outside04/21/2014Ongoing8:00 p.m.- 7:00 a.m.22.00FT 9.00Width Restriction - Southbound Lanes Only. Constructing new bridge
4Washington4928063.7465.03North Bound Inside04/21/2014Ongoing8:00 p.m-6:00 a.m.22.00FT 9.00Width Restriction - Northbound Lanes Only. Constructing new bridge.
4Washington4928063.7465.03North Bound Outside05/21/2014Ongoing8:00 PM - 6:00 AM11.00FT 9.00Width Restriction - Northbound Lanes Only. Constructing new bridge.
Dist.CountyRouteSectionBegin Mile MarkerEnd Mile MarkerLane(s) ClosedBegin DateApprox. DaysTimeHor. Clr.UnitVert. Clr.Max. Width LoadComments................
9Benton4929083.1185.65Alternating North & South Bound11/03/2014ONGOING9pm - 6am Sun-Thu FT 12.00Ongoing Lane Closure Sun. - Thursdays for construction vehicles entering and exiting the median.
1Crittenden551103.436.80North Bound Outside03/06/2014Ongoing24 Hours11.00FT 8.50For work associated with project BB0108.
1Crittenden551104.567.34South Bound Outside01/27/2014Ongoing24 Hours13.50FT 8.50Lane Closure for Deck Overlay and Roadway work associated with BB0108
10Mississippi5512040.8641.00South Bound Inside12/01/201457:30AM-3:00PM FT 14.00H.B.M. Crews cleanting and painting Bridge
9Benton620209.6511.05West Bound11/22/201457:30 AM - 6:30 PM FT  Asphalt Operations.
9Benton6202013.4514.27Alternating East & West Bound10/22/2014367am - 6:30 pm FT  Ashpalt paving operations- Job 090065
2Jefferson6313B0.660.80South Bound07/31/201415024 hours FT  Closed due to building collapse. Will be reopened after building is stabilized.
7Bradley6317028.0028.60Alternating North & South Bound11/25/201428:00Aa.m.-3:00p.m.18.00FT 15.00Inspection of the Hwy 63 Ouachita River Bridge by HBM
8Pope6406010.5011.00Alternating East & West Bound10/13/2014ongoing6 p.m. - 6 a.m.9.00FT 9.00Asphalt Paving Operation.
5Stone6602014.2615.52East & West Bound06/04/2014Ongoing24 hours10.00FT13.5010.00AHTD Job 050231 12.)Alternating Lane Closure 32.)Wide Loads use Alternate Route
Dist.CountyRouteSectionBegin Mile MarkerEnd Mile MarkerLane(s) ClosedBegin DateApprox. DaysTimeHor. Clr.UnitVert. Clr.Max. Width LoadComments................
3Hempstead670205.8311.96Alternating East & West Bound09/24/2014Ongoing24 Hrs FT 9.00Job 030442 Asphalt Paving Operation. Width Restriction - All Lanes. NO WIDE LOADS
6Pulaski671007.008.50North Bound Inside08/15/2014Ongoing24 Hours FT 10.00Job 061276 Temporary Widening in Median
6Pulaski671008.009.50South Bound Inside08/15/2014Ongoing24 Hours FT 10.00Job 061276 Temporary Widening in Median
6Pulaski671009.2515.33North Bound Center & Outside11/20/201419 A.M. - 3 P.M.12.00FT 9.00Consultant FWD Testing for CAP jobs
6Pulaski671009.2515.33South Bound Center & Outside11/21/201419 A.M. - 3 P.M.12.00FT 9.00Consultant FWD Testing for CAP jobs
6Pulaski671009.5015.34North Bound Outside07/23/2014Ongoing7:00 pm to 8:00 am FT 12.00Job 061424 Concrete pavement patching
6Pulaski6710011.0015.00South Bound Outside07/23/2014Ongoing6:00 pm to 5:00 am FT 12.00Job 061424 Concrete pavement patching
6Lonoke671100.000.55North Bound Center & Outside11/24/201429 A.M. - 3 P.M.12.00FT 9.00Consultant FWD Testing for CAP jobs
6Lonoke671100.001.50South Bound Outside09/08/2014Ongoing6:00 pm to 5:00 am FT 12.00Job 061424 Pavement Patching
6Lonoke671100.000.55South Bound Center & Outside11/24/201429 A.M. - 3 P.M.12.00FT 9.00Consultant FWD Testing for CAP jobs
Dist.CountyRouteSectionBegin Mile MarkerEnd Mile MarkerLane(s) ClosedBegin DateApprox. DaysTimeHor. Clr.UnitVert. Clr.Max. Width LoadComments................
6Lonoke671100.001.00North Bound Outside09/08/2014Ongoing7:00 pm to 8:00 am FT 12.00Job 061424 Pavement patching
5White671304.199.51North Bound07/24/2014ongoing2417.00FT 14.00Pavement Removal in NB. Head to head traffic in SB
6Prairie701607.8219.84East & West Bound07/21/2014Ongoing24 hours11.00FT 8.50Related to Job BB0101. Width Restriction - All Lanes
1Monroe701700.007.70East & West Bound07/21/2014Ongoing24 Hours11.00FT 8.50Related to Job BB0101. Width Restriction - All Lanes.
4Sebastian711404.306.10Alternating North & South Bound11/19/2014324 Hours12.00FT 9.00Job 040376 NB and SB Inside Lanes For ACHM Leveling and Signal Loops
2Ashley820800.000.30Alternating East & West Bound11/24/201427:30a,m.-3:00pm FT 20.00Bridge repairs. Performed by H.B.M. Crew B4502
8Conway950102.794.02Alternating North & South Bound02/24/2014Ongoing24 Hours13.00FT 10.00Left and Right Shoulder work. Width Restriction - All Lanes.
6Pulaski1000003.224.29East Bound Outside07/31/2013Ongoing9 AM - 9 PM18.00FT 18.00061301 - Mon-Fri only; Contact Permits on removal
8Johnson1030100.000.60North & South Bound08/07/2013ongoing24 Hours11.00FT 11.00Width Restriction - All Lanes. Installation of Centerline Islands with Light Poles
4Logan1090307.759.41Alternating North & South Bound09/01/2014Ongoing24 Hours15.00FT 12.00Construction of water main attachement to bridge. Width restriction only.
Dist.CountyRouteSectionBegin Mile MarkerEnd Mile MarkerLane(s) ClosedBegin DateApprox. DaysTimeHor. Clr.UnitVert. Clr.Max. Width LoadComments................
4Washington1120002.412.55Alternating East & West Bound11/17/2014258:00 a.m.-7:00 p.m.11.00FT 9.00Just Width Restriction - All Lanes. Utility work. No wide Load. No lanes closures.
2Ashley16501021.1721.27Alternating North & South Bound07/09/20141807 am - 7 pm FT25.00 Safety platform in place reducing vertical clearance. - overpass construction for job 020509
7Dallas1670704.497.50Left Shoulder07/09/2014Ongoing24 Hours12.00FT 9.00Width restriction related to Job 070289. 12 ft. lane with no shoulder for SB Lanes
7Cleveland1670800.000.35Left Shoulder07/09/2014Ongoing24 Hours12.00FT 9.00Width restriction related to Job 070289. 12 ft. lane with no shoulder for SB Lanes
7Cleveland1670806.908.71Width Restriction Only02/07/2013Ongoing24 Hours FT 12.00Width Restriction in NB and SB lanes due to Construction job 070291
7Dallas1670900.002.30Width Restriction Only02/07/2013Ongoing24 Hours FT 12.00Width Restriction in NB and SB lanes due to Construction Job 070291
9Baxter1770102.392.86South Bound12/31/201418324 Hours10.00FT 10.00Temp. signals will be used. Open Holidays
5Cleburne2250301.421.97All08/05/2013Ongoing24 Hours FT18.00 Steel Girders are being hung for the new Bridge on AHTD Job 050228 which goes over Hwy. 225.
4Washington2650204.736.70North Bound Center07/15/2013Ongoing9:00a.m.-3:00p.m.11.00FT 11.00Width Restriction - All Lanes. No Turning Lane.
4Washington4120205.305.85West Bound Outside11/20/201417:00 p.m.-6:00 a.m.24.00FT 11.00Width Restriction - Westbound Lanes Only. Repairing signal loop wires at Barrington Rd.
Dist.CountyRouteSectionBegin Mile MarkerEnd Mile MarkerLane(s) ClosedBegin DateApprox. DaysTimeHor. Clr.UnitVert. Clr.Max. Width LoadComments................
2Lincoln4250505.305.38Right Shoulder07/16/2014on24 Hours FT 24.00Shoulder closed due to shoulder notched
6Pulaski4302100.390.53Right Shoulder08/21/2014Ongoing24 Hours FT 18.00Job 061332 Precast Barrier Wall installed on outside shoulder
6Pulaski4302105.136.42South Bound Outside11/02/2014Ongoing24 Hours FT  Job 061244 4th lane extension
6Pulaski43021011.6012.98North Bound Inside12/01/201459 PM - 7 AM12.00FT 10.00Job CA0609 precast barrier wall installation
6Pulaski43021011.6012.98Width Restriction Only11/18/2014Ongoing24 Hours FT 8.00Precast barrier wall for widening of bridge
6Pulaski5300100.008.50Width Restriction Only10/07/2014Ongoing24 Hours12.00FT 8.50Width Restriction - Southbound Lanes Job BB0613.
6Pulaski5300101.258.50Width Restriction Only10/17/2014Ongoing24 Hours12.00FT 9.00Job BB0613 Precast barrier wall for head-to-head traffic NB lanes
2Jefferson53005017.7823.77North Bound Outside10/13/2014456:00 a.m. - 6:00 p.m. FT 14.00Striping/Pavement Marking Placement.
2Jefferson53005017.7823.77South Bound Outside10/13/2014456:00 a.m. - 6:00 p.m. FT 14.00Striping/Pavement Marking Placement.
2Jefferson53005023.6023.70South Bound Inside11/12/2014ongoing2412.00FT 12.00Pavement repairs.
Dist.CountyRouteSectionBegin Mile MarkerEnd Mile MarkerLane(s) ClosedBegin DateApprox. DaysTimeHor. Clr.UnitVert. Clr.Max. Width LoadComments................
6Pulaski6302107.397.40East Bound08/11/2013ongoing24 hrs FT  Job 061244: No left turn EB Financial Centre Parkway to NB Shackleford. Detour in place.
6Pulaski6302107.397.40West Bound02/17/2013ongoing24 hrs FT  Job 061244: No left turn WB I-630 to SB Shackleford Rd. Detour in place.
6Pulaski6302107.397.40North Bound08/10/2013ongoing24 hrs FT  Job 061244: No left turn NB Shackleford to WB Financial Centre Parkway. Detour in place.